INNOVATIVE MOORING CONNECTION SYSTEM

4 January 2017

In 2013 Dana Petroleum awarded Balmoral Offshore Engineering a contract to design and manufacture key components for a pioneering mooring system to be used on its Western Isles project in the challenging..

DEEP GULF ENERGY – KODIAK

12 October 2015

Located on Mississippi Canyon Block 773, the Devil’s Tower Spar services as a production hub for multiple subsea tiebacks. ENI serves as the operator of the facility.

KIZOMBA C FPSO MOORING RAPID RESPONSE PLAN (MRRP)

10 August 2015

Based on the ongoing success of Delmar Systems’ temporary replacement mooring system for ExxonMobil’s Serpentina FPSO offshore Equatorial Guinea, ExxonMobil contracted Delmar Systems to develop the temporary emergency moorings for both FPSO..

Chevron – Bigfoot

12 June 2015

Between Friday, May 29 and Sunday, May 31, 2015, several pre-installed tendons of the Big Foot platform lost buoyancy and sank to the bottom on the ocean.

Gryphon Alpha FPSO connection

4 August 2014

Delmar Systems was awarded the 3D field real-time modelling of the Gryphon Alpha FPSO mooring lines during reconnection in a heavily congested field..

EXXONMOBIL KARA SEA ARCTIC MOORING

13 April 2014

Delmar Systems was contracted to provide mooring services for the West Alpha on ExxonMobil’s University location in the Kara Sea. Operational mooring procedures for the preset mooring installation and rig connection were..

SHELL CARDAMOM PIPELINE INITIATION

23 March 2014

The Noble Jim Thompson MODU provided drilling and completion services for the Shell Cardamom development. The rig presented a number of unique challenges including a relatively close proximity to the Auger TLP..

SAIPEM BIGFOOT PIPELINE INITIATION PILE

4 December 2013

The Bigfoot TLP (Chevron) export lines were installed by Saipem using the newly constructed Castorone pipelay vessel. The project required the first end SCR installation to start in the deepwater location and..

WOODSIDE – MOORING QRA TOOL

2 October 2013

Woodside contracted Delmar Systems to develop a mooring quantitative risk assessment (QRA) tool capable of assessing possible threats from mooring failure.